Paul Taylor Building Services Ltd

Company Registration No: 7389944

 Email me for a Free Estimate

or phone me on 01269 593149 or Mobile: 07788 724995


Home              Portfolio           Email Paul

Beam & Block Floor

Building a Timber Frame House

The beams were lifted into position and blocks were laid to form the floor. This method was used because the infill was over the permissible depth. The advantages are that construction is very fast, in this case only two days work for two men. A dpc had to be laid beneath the beams and underfloor spaces adequately ventilated. On this build a Radon barrier was not needed.

Cost is slightly higher using this method, but construction is faster and cleaner.

Beam & Block

The garage area can be seen to the lower right of the above picture

Beam & Block

Laying the blocks


© 2004/2005 Paul Taylor Site updated 28 January 2011   Webmaster