Building a timber frame house

Site description  

Site clearance & footings  

Services

 Slab/DPC

Beam & Block Floor  

Scaffolding

Timber Frame 

 Ground floor & Studding

First floor walls & studding

Roof

Roof - Tiling

 Wiring

Floors

Kitchen

Exterior fittings

Garage/Bed 5

Garage roof detail

Porch detail

Exterior painting

Garage doors

Garden clean up

Rear Garden in August

Kitchen - Tiling

Kitchen - Island unit

Kitchen - Wine rack

Kitchen - door

Stairs

Bathroom

En-suite shower

Boiler

Porch disability slope

Soils & soakaway

Bathroom

Hall & Stairs

Bed 5

Cloakroom detail

En-suite

En-suite

Drive

Lounge

Consumer unit

Fireplace

Decking

 

Progress of Build

2004

June - December

2005

January   February   March   April   May   June    July   

August    September   October    November     Building a timber frame house

2004

January    February

This house was constructed by Paul Taylor Building Services and has a full NHBC guarantee. Sub-contractors were used for the blockwork and rendering.

These pages show the progress of the build from start to finish in 2006.


The site was purchased in mid-2004 with outline planning consent. A large mobile home was placed on site and initial work included clearing trees and vegetation, fencing and the installation of sewerage, water and telephone services. Neatwood Homes were engaged to supply the plans and the timber frame. This comes as a package and it was decided at the outset to have Neatwood construct the timber frame once the walls were up to DPC level.

Tolerance for the slab is ± 5mm and a laser levelling device was used to provide accuracy.

Final plans were approved by October and groundwork began in mid-November. Gelli Plant carried out the excavation for the footings and excess spoil was removed by another local contractor. RMC supplied the 20 cubic metres of concrete for the footings and garage base; concrete building blocks were supplied by Tygroes. Other suppliers are:

B&Q Superstore, Swansea [Bathroom & En-suite fittings]

Brandon Hire [mini digger, levelling equipment, etc.]

Coopers, Ammanford [soil and drainage pipework]

Howden Joinery, Carmarthen [Kitchen and appliances]

LBS Ammanford [bricks, blocks, cement, timber]

Scaffolding A & E Scaffolding

TLC Swansea [electrical fittings]

Kingsbury, Cross Hands [electrical fittings and cabling]

Wickes [Swansea]

The build was completed by end of December 2005 - and all that remained to do was build decking at the rear and make the front entrance gates. There were a few delays during the build but these were in the main due to weather conditions.

The build

 2004

June 

Site purchased

 

August  

Temporary electric, sewerage and telephone

services installed.

Caravan placed on site and initial clearance.

Fencing erected.

Plans submitted to local authority

2004

September

Clearing and getting the site ready

2004

October

Final Plans approved

 

November 11

                 12

 

                 13

                 14

                 15

             16-31

Final site clearance, footings dug.

Footings passed by Building Inspector.

Footings passed by NHBC Inspector.

Footings poured.

Below ground blockwork set out.

Blockwork commenced

Blockwork raised to ground level

Air vents installed

2004

December 1

                 5

                 6

                 7

                 8

 

9

10

16

 

17

20

21

22

29

 

Oversite levelled and general clear up

Soil pipes and water services laid

Plastic sheet laid on oversite

Floor beams lifted in

Blocks laid in floor beams

Garage floor levelled & dpc laid

Garage floor poured

Final finishing of the slab

Scaffolding arrived and erected

Frame arrived & construction began

Ground floor walls & studding

First floor walls & studding

Roof trusses fitted & braced

Roof erected and Felted & battened

Work stops for Xmas and site tidied

External Doors and windows fitted

Front door - interior

Velux installed

2005

January 9

 

12

14

15

Completion of frame

Garage - gable end

Wiring - first fix

Roof tiles delivered

Tiling started

2005

February 1

 1

4

 

 

15

20

22

25-28

Interior garage wall built

Finished roof

First fix wiring completed

First-fix CH and water services completed

Floors laid

Insulation delivered

250 Plasterboards delivered

Kitchen delivered

Insulation installed

2005

March 1-5

7

8-31

Kitchen installed

Bricklayers due to start on exterior walls

Bad weather slowed blockwork down

Bathroom and spa bath fitted

En-suite fitted and shower installed

Dry-lining detail

NHBC and Building Regs checks passed

2005

April 1 - 20

21- 30

More delays due to bad weather

Kitchen almost finished

Landing storage

Lounge

Brick piers built for porch overhang

Brick Quoins

Internal doors fitted

Staircase & balustrade fitted

Skirtings and architraves fitted

Garage/Bed 5

Bracing - garage roof

Valley on garage roof

Window installed in garage gable end

Soffits and fascias fitted to garage

All rooms coved

Study

2005

May 1 - 8

 

 

 

9

14 - 15

16-31

 

 

Last stages of blockwork

Garage roof felted and battened

5th bedroom

Mist coat applied to four bedrooms

Sub-contractor begins rendering blockwork

Garage roof tiling started

Upstairs skirtings and architraves fitted

Blockwork rendering completed

Garage roof tiling completed

2005

June 1

2-5

6-7

8-30

 

 

 

 

 

Porch detail

Outside painting completed

Garage doors and scaffold removal

All scaffolding removed

Soils and Soakaway

Boiler connected

Fireplace in lounge

Final decoration to all upstairs rooms

Sockets fitted to all upstairs rooms

Bathroom & en-suite completed

Garden part levelled and seeded

2005

July 1

14

21

23

24

 

 

Decorating continues

Consumer unit

Porch - slope base

Boiler fitted and connected

Kitchen tiled

Kitchen door

Wine Rack

Laminate floor laid in kitchen

2005

August 6

7

Utility room dry lined

Bed 5 dry lined

Rear garden

2005

September

Ramp to front door laid

Last few radiators connected

Decoration of all upstairs rooms completed

Decoration of all downstairs rooms completed

2005

October

 

 

30

Laminate floor to Hall and Utility laid

Utility room fitted out and decorated

Garage fitted out with bench & shelving

All outstanding interior work complete

2005

November

8

 

NHBC and Building Regs Finals passed

Drive and decking to be completed

Caravan to be removed

2005

December

The completed En-suite

Caravan removed

General clear up of site

2006

 

 

January

 

February

Gravel laid on drive

Side access gates made and hung

Final Touches: Decking  Porch  Bathroom  Bed 5 

Lounge  Kitchen  Cloakroom  En-suite 

Landing detail   Entrance Hall   Decking

    