Building a timber frame house
|
|
Progress of Build
|
2004 |
|
|
2005 |
January February March April May June July August September October November Building a timber frame house |
|
2004 |
This house was constructed by Paul Taylor Building Services and has a full NHBC guarantee. Sub-contractors were used for the blockwork and rendering.
These pages show the progress of the build from start to finish in 2006.
The site was purchased in mid-2004 with outline planning consent. A large mobile home was placed on site and initial work included clearing trees and vegetation, fencing and the installation of sewerage, water and telephone services. Neatwood Homes were engaged to supply the plans and the timber frame. This comes as a package and it was decided at the outset to have Neatwood construct the timber frame once the walls were up to DPC level.
Tolerance for the slab is ± 5mm and a laser levelling device was used to provide accuracy.
Final plans were approved by October and groundwork began in mid-November. Gelli Plant carried out the excavation for the footings and excess spoil was removed by another local contractor. RMC supplied the 20 cubic metres of concrete for the footings and garage base; concrete building blocks were supplied by Tygroes. Other suppliers are:
B&Q Superstore, Swansea [Bathroom & En-suite fittings]
Brandon Hire [mini digger, levelling equipment, etc.]
Coopers, Ammanford [soil and drainage pipework]
Howden Joinery, Carmarthen [Kitchen and appliances]
LBS Ammanford [bricks, blocks, cement, timber]
Scaffolding A & E Scaffolding
TLC Swansea [electrical fittings]
Kingsbury, Cross Hands [electrical fittings and cabling]
Wickes [Swansea]
The build was completed by end of December 2005 - and all that remained to do was build decking at the rear and make the front entrance gates. There were a few delays during the build but these were in the main due to weather conditions.
| 2004 |
June |
Site purchased |
|
August |
Temporary electric, sewerage and telephone services installed. Caravan placed on site and initial clearance. Fencing erected. Plans submitted to local authority |
|
|
2004 |
September |
|
|
2004 |
October |
Final Plans approved |
|
November 11 12
13 14 15 16-31 |
Final site clearance, footings dug. Footings passed by Building Inspector. Footings passed by NHBC Inspector. Footings poured. Below ground blockwork set out. Blockwork commenced Blockwork raised to ground level Air vents installed |
|
|
2004 |
December 1 5 6 7 8
9 10 16
17 20 21 22 29
|
Oversite levelled and general clear up Soil pipes and water services laid Plastic sheet laid on oversite Floor beams lifted in Garage floor levelled & dpc laid Garage floor poured Final finishing of the slab Scaffolding arrived and erected Frame arrived & construction began Roof erected and Felted & battened Work stops for Xmas and site tidied |
|
January 9
12 14 15 |
Completion of frame Roof tiles delivered |
|
|
2005 |
1 4
15 20 22 25-28 |
First fix wiring completed First-fix CH and water services completed Insulation delivered 250 Plasterboards delivered Kitchen delivered |
|
2005 |
7 8-31 |
Bricklayers due to start on exterior walls Bad weather slowed blockwork down En-suite fitted and shower installed NHBC and Building Regs checks passed |
|
2005 |
21- 30 |
More delays due to bad weather Brick piers built for porch overhang Internal doors fitted Skirtings and architraves fitted Window installed in garage gable end Soffits and fascias fitted to garage All rooms coved |
|
2005 |
9 14 - 15 16-31
|
Garage roof felted and battened Mist coat applied to four bedrooms Sub-contractor begins rendering blockwork Garage roof tiling started Upstairs skirtings and architraves fitted Blockwork rendering completed Garage roof tiling completed |
|
2005 |
2-5 6-7 8-30
|
Garage doors and scaffold removal All scaffolding removed Final decoration to all upstairs rooms Sockets fitted to all upstairs rooms Bathroom & en-suite completed |
|
2005 |
14 21 23 24
|
Decorating continues |
|
2005 |
7 |
Utility room dry lined Bed 5 dry lined |
|
2005 |
Ramp to front door laid Last few radiators connected Decoration of all upstairs rooms completed Decoration of all downstairs rooms completed |
|
|
2005 |
30 |
Laminate floor to Hall and Utility laid Utility room fitted out and decorated Garage fitted out with bench & shelving All outstanding interior work complete |
|
2005 |
8 |
NHBC and Building Regs Finals passed Drive and decking to be completed Caravan to be removed |
|
2005 |
Caravan removed General clear up of site |
|
|
2006
|
|
Side access gates made and hung Final Touches: Decking Porch Bathroom Bed 5 |